|
As stated previously, there
were to be three nuclear reactors (Piles) built at Hanford. They
were to be designated as Piles B, D and F.
Groundbreaking for the
water-cooling plant for the 100-B pile, the westernmost of the three,
took place on August 27, 1943, less than two weeks before Italy's
surrender to the Allies. Work on the pile itself began in
February 1944, with the base and shield being completed by
mid-May. It took another month to place the graphite pile and
install the top shield and two more months to wire and pipe the pile
and connect it to the various monitoring and remote control devices.
Once operational, uranium
slugs, produced at a nearby facility, would drop into water pools
behind the 100-B Pile after being irradiated. From these pools,
the highly-radioactive slugs would be moved by remote-controlled rail
cars to a storage facility five miles away. Next they would make
their way to their final destination at one of the two enormous
chemical separation locations, designated 200-West and 200-East.
200-West was comprised of two separation facilities, the T and U
units, while a single plant, the B unit, made up the 200-East
complex. (A planned fourth separation plant at 200-East was
never built).
With the abandonment of the
"plutonium gun bomb" in July 1944, planning at Hanford
became much more complicated. Pile 100-B was almost complete, as
was the first chemical separation plant (T Unit), while Pile D was at
the halfway point. Pile F was not yet under construction.
If the newly theoretical implosion devices using plutonium could be
developed at Los Alamos, the three piles would probably produce enough
plutonium for the weapons required, but as yet no one was sure of the
amount needed.
Excitement mounted at
Hanford as the date for pile start-up approached. Enrico Fermi
placed the first uranium slug in pile 100-B on September 13,
1944. Final checks on the pile had been uneventful. The
scientists could only hope that they were accurate, since once the
pile was operational the intense radioactivity would make maintenance
of many components impossible. Loading slugs and taking
measurements took a full two weeks. From just after midnight
until approximately 3:00 a.m. on September 27, the pile ran without
incident at a power level higher than any previous chain reaction
(though only at a fraction of design capacity). The operators
were elated, but their excitement turned to astonishment when the
power level began falling after three hours. It fell
continuously until the pile ceased operating entirely on the evening
of the 28th. By the next morning the reaction began again,
reached the previous day's level, then dropped.
|