|
Lawrence and his colleagues
continued to look for ways to improve the electromagnetic
process. Lawrence found that hot (high positive voltage)
electrical sources could replace the single cold (grounded) source in
future plants, providing more efficient use of power, reducing
insulator failure, and making it possible to use multiple rather than
single beams. Meanwhile, receiver design evolved quickly enough
in spring and summer 1943 to be incorporated into the Alpha
plant. Work at the Radiation Laboratory picked up additional
speed in March with the authorization of the Beta process. With
Alpha technology far from perfected, Lawrence and his staff now had to
participate in planning for an unanticipated stage of the
electromagnetic process.
While the scientists in
Berkeley studied changes that would be required in the down-sized Beta
racetracks, engineering work at Oak Ridge prescribed specific design
modifications. For a variety of reasons, including simplicity of
maintenance, Tennessee Eastman decided that the Beta plant would
consist of a rectangular, rather than oval, arrangement of two tracks
of thirty-six tanks each. Factoring this configuration into
their calculations, Lawrence and his coworkers bent their efforts to
developing chemical processing techniques that would minimize the loss
of enriched uranium during Beta production runs. To make certain
that Alpha had enough feed material, Lawrence arranged for research on
an alternate method at Brown University and expanded efforts at
Berkeley. With what was left of his time and money in early 1943
Lawrence built prototypes of both Alpha and Beta units at Berkeley for
testing and training operating personnel. Meanwhile Tennessee
Eastman, running behind schedule, raced to complete experimental
models so that training and test runs could be performed at Oak Ridge.
But in the midst of
encouraging progress in construction and research on the
electromagnetic process in July came discouraging news from
Oppenheimer's isolated laboratory in Los Alamos, set up in 1943 to
consolidate work on atomic weapons. Oppenheimer warned that
three times more fissionable material would be required for a bomb
than earlier estimates had indicated. Even with satisfactory
performance of the racetracks, it was now possible that they might not
produce enough purified uranium 235 in time.
Lawrence responded to this
crisis in characteristic fashion: He immediately lobbied Groves
to incorporate multiple sources into the racetracks under construction
and to build even more racetracks. Groves decided to build the
first four as planned but, after receiving favorable reports from both
Stone & Webster and Tennessee Eastman, allowed a four-beam source
in the fifth. Convinced that the electromagnetic process would
work and sensing that estimates from Los Alamos might be revised
downward in the future, Groves let Lawrence talk him into building a
new plant - in effect, doubling the size of the Y-12 complex.
The new facility, Groves reported to the Military Policy Committee on
September 9, would consist of two buildings, each with two rectangular
racetracks of ninety-six tanks operating with four-beam sources.
Shakedown at Y-12
During the
summer and fall of 1943 the first electromagnetic plant began to take
shape. The huge building to house the operating equipment was
readied as manufacturers began to deliver everything from electrical
switches to motors, valves, and tanks. While construction forces
now totaled more than 15,000 people, another 5,000 operating and
maintenance personnel were hired and trained. Then between October
and mid-December, Y-12 paid the price for being a new technology that
had not been put through its paces in a pilot plant. Vacuum tanks
in the first Alpha racetrack leaked and shimmied out of line due to
unforeseen tremendous magnetic forces, welds failed, electrical circuits
malfunctioned, and operators made frequent and costly mistakes.
Most seriously, the magnet coils shorted out because of rust and
sediment in the cooling oil.
Groves arrived
on December 15 and shut the entire racetrack down. The coils were
sent back to Allis-Chalmers with hope that they could be cleaned without
being dismantled entirely, while measures were taken to prevent
recurrence of the shorting problem. The second Alpha track now
bore the weight of the electromagnetic effort. In spite of
precautions aimed at correcting the electrical and oil related problems
that had shut down Alpha 1, the second Alpha fared little better when it
started up in mid-January 1944. While all tanks operated at least
for short periods, performance was sporadic and maintenance could not
keep up with the electrical failures and defective parts. Like its
predecessor, Alpha 2 was a maintenance nightmare.
Alpha 2
eventually produced about 200 grams of twelve-percent uranium 235 by the
end of February 1944, enough to send samples to Los Alamos as well as
feed the new Beta unit but not enough to satisfy estimates of weapon
requirements. The first four Alpha tracks did not operate together
until April, a full four months behind schedule. While maintenance
improved, output was well under previous expectations. The opening
of the Beta building on March 11, 1944 led to further
disappointment. Beam resolution was so unsatisfactory that a
complete redesign was required. To make matters worse, word spread
that the K-25 gaseous diffusion process was in deep trouble because of
its ongoing barrier crisis. K-25 had been counted upon to provide
uranium enriched enough to serve as feed material for the Beta
tracks. Now it would be producing such slight enrichment that the
Alpha tracks would have to process K-25's material, requiring extensive
redesign and retooling of tanks, doors and liners, particularly in units
that would be wired to run as hot, rather than as cold electrical
sources.

|