|
Although the Lewis
Committee report had placed gaseous diffusion ahead of the
electromagnetic approach, many were still betting in early 1943 that
Lawrence and his mass spectrograph would eventually predominate.
Lawrence and his laboratory of mechanics at Berkeley continued to
experiment with the giant 184-inch magnet, trying to reach a consensus
on which shims, sources, and collectors to incorporate into the Y-12
design for the Oak Ridge plant. Research on magnet size and
placement and beam resolution eventually led to a
"racetrack" configuration of two magnets with forty-eight
gaps containing two vacuum tanks each per building, with ten buildings
being necessary to provide the 2,000 sources and collectors needed to
separate 100 grams of uranium 235 daily. It was hoped that
improvements in calutron design, or placing multiple sources and
collectors in each tank, might increase efficiency and reduce the
number of tanks and buildings required, but experimental results were
inconclusive even as Stone & Webster of Boston, the Y-12
contractor, prepared to break ground.
At a meeting of Groves,
Lawrence, and John Lotz of Stone & Webster in Berkeley late in
December 1942, Y-12 plans took shape. It was agreed that Stone
& Webster would take over design and construction of a 500-tank
facility, while Lawrence's laboratory would play a supporting role by
supplying experimental data. By the time another summit
conference on Y-12 took place in Berkeley on January 13 and 14, Groves
had persuaded the Tennessee Eastman Company to sign on as plant
operator and arranged for various parts of the electromagnetic
equipment to be manufactured by the Westinghouse Electric Company, the
Allis-Chalmers Manufacturing Company and the Chapman Valve
Manufacturing Company. At the same time, General Electric agreed
to provide electrical equipment.
On January 14, after a day
of presentations and a demonstration of the experimental tanks in the
cyclotron building, Groves stunned the Y-12 contractors by insisting
that the first racetrack of ninety-six tanks be in operation by July 1
and that 500 tanks be delivered by year's end. Given that each
racetrack assembly was 122 feet long, 77 feet wide and 15 feet high;
that the completed plant was to be the size of three, large two-story
buildings; that tank design was still in flux; and that chemical
extraction facilities also would have to be built, Groves' demands
were little less than shocking. Nonetheless, Groves maintained
that his schedule could be met.
For the next two months
Lawrence, the contractors, and the Army negotiated over the final
design. While all involved could see possible improvements,
there simply was not enough time to incorporate every suggested
modification. Y-12 design was finalized at a March 17 meeting in
Boston, with one major modification - the inclusion of a second stage
of the electromagnetic process. The purpose of this second stage
was to take the enriched uranium 235 derived from several runs of the
first stage and use it as the "feed material" for a second
stage of racetracks containing tanks approximately half the size of
those in the first. Groves approved this arrangement and work
began on both the Alpha (first-stage) and Beta (second-stage) tracks.
Groundbreaking for the
Alpha plant took place on February 18, 1943. Soon blueprints
could not be produced fast enough to keep up with construction as
Stone & Webster labored to meet Groves' deadline. The Beta
facility was actually begun before formal authorization. While
laborers were aggressively recruited, there was always a shortage of
workers skilled enough to perform jobs according to the rigid
specifications. (A further complication was that some tasks could be
performed only by workers with special security clearances).
Huge amounts of material had to be obtained (38 million board feet of
lumber, for instance), and the magnets needed so much copper for
windings that the Army had to borrow close to 15,000 tons of silver
bullion from the United States Treasury to fabricate into strips and
wind onto coils as a substitute for copper. Treasury silver was
also used to manufacture the busbars that ran around the top of the
racetracks.
Replacing copper with
silver solved the immediate problem of the magnets and busbars, but
persistent shortages of electronic tubes, generators, regulators, and
other equipment plagued the electromagnetic project and posed the most
serious threat to Groves' deadline. Furthermore, last minute
design changes continued to frustrate equipment manufacturers.
Nonetheless, when Lawrence toured with Y-12 contractors in May of
1943, he was impressed by the scale of operations. Lawrence
returned to Berkeley rededicated to the "awful job" of
finishing the racetracks on time.

|