|
The fall 1942 planning sessions at the Met Lab led to the decision to
build a second Fermi experimental pile at Argonne as soon as his
experiments on the first (CP-1) were completed and to proceed on
design of the Mae West helium-cooled unit. When DuPont engineers
assessed the Met Lab's plans in the late fall, they agreed that helium
should be given first priority. They placed heavy water second
and urged an all-out effort to produce more of this highly effective
moderator. Bismuth and water were ranked third and fourth in
DuPont's analysis.
Priorities changed when
Fermi's calculations demonstrated a higher value of "k"
than anyone had anticipated. Met Lab scientists concluded that a
water-cooled pile was now feasible, while DuPont shifted its interest
to air cooling. Since a helium-cooled unit shared important
design characteristics with an air-cooled one, Greenwalt thought that
an air-cooled semi-works at Oak Ridge would contribute significantly
to designing the full-scale facilities at Hanford.
DuPont established the
general specifications for the air-cooled semi-works and chemical
separation facilities in early 1943. A massive graphite block,
protected by several feet of concrete, would contain hundreds of
horizontal channels filled with uranium slugs surrounded by cooling
air. New slugs would be pushed into the channels on the face of
the pile, forcing the irradiated ones at the rear to fall into an
underwater bucket. The buckets of irradiated slugs would undergo
radioactive decay for several weeks, then be moved by an underground
canal into the separation facility where the plutonium would be
extracted using remote control equipment.
Met Lab activities focused
on designing a water-cooled pile for the full-scale plutonium
plant. Taking their cue from the DuPont engineers, who utilized
a horizontal design for the air-cooled semi-works, Met Lab scientists
abandoned the vertical arrangement with water tanks, which had posed
serious engineering difficulties. Instead they proposed to place
uranium slugs sealed in aluminum cans inside aluminum tubes. The
tubes, laid horizontally through a massive graphite block, would cool
the pile with water injected into each tube, The pile,
containing 200 tons of uranium and 1,200 tons of graphite, would need
75,000 gallons of fresh water per minute for cooling.
Pushing for a Decision on Pile
Design
Greenwalt's initial
response to the water-cooled design was guarded. He worried
about pressure problems that might lead to boiling water in individual
tubes, corrosion of the slugs and tubes, and the one-percent margin of
safety for "k". But he was even more worried
about the proposed helium-cooled model. He feared that the giant
compressors would not be ready in time for Hanford to come on-line,
that the shell could not be made vacuum-tight, and that the pile would
be extremely difficult to operate. DuPont engineers conceded
that Greenwalt's fears were well-founded. Late in February 1943,
Greenwalt reluctantly concluded that the Met Lab's model, while it had
its problems, was superior to DuPont's own helium-cooled design and
decided to adopt the water-cooled approach.
The Met Lab's victory in
the pile design competition came as its status within the Manhattan
Project was changing. Still an exciting place intellectually,
the Met Lab occupied a less central place in the bomb project as Oak
Ridge and Hanford rose to prominence. Fermi continued to work on
the Stagg Field pile (CP-1), hoping to determine the exact value of
"k". Subsequent experiments at the Argonne site
using CP-2, built with material from CP-1, focused on neutron capture
probabilities, control systems, and instrument reliability. Once
the production facilities at Oak Ridge and Hanford were underway,
however, Met Lab research became increasingly unimportant in the race
for the bomb and the scientists found themselves serving primarily as
consultants to DuPont.
A Decision on Chemical Extraction
While the Met Lab
physicists chafed under DuPont domination, a smoother and quieter
relationship existed between the chemists and DuPont. Seaborg
and Cooper continued to work well together, and enough progress was
made in the semi-works for the lanthanum fluoride process in late 1942
that DuPont moved into the plant design stage and converted the
semi-works for the bismuth phosphate method. DuPont pressed for
a decision on plutonium extraction methods in late May 1943.
Greenwalt chose bismuth phosphate, though even Seaborg admitted he
could find little to distinguish between the two. Greenwalt
based his decision on the corrosiveness of lanthanum fluoride and on
Seaborg's guarantee that he could extract at least fifty percent of
the plutonium using bismuth phosphate. DuPont began constructing
the chemical separation pilot plant at Oak Ridge, while Seaborg
continued refining the bismuth phosphate method.
It was now Cooper's job to
design the pile as well as the plutonium extraction facilities at
Clinton, both complicated engineering tasks made even more difficult
by high levels of radiation produced by the process. Not only
did Cooper have to oversee the design and fabrication of parts for yet
another new Manhattan Project technology, he had to do so with an eye
toward planning the Hanford facility. Safety was a major
consideration because of the hazards of working with plutonium, which
was highly radioactive. Uranium, a much less active element than
plutonium, posed far fewer safety problems.
In July of 1942 Compton had
established a new health division at the Met Lab and put Robert S.
Stone in charge. Stone established emission standards and
conducted experiments on radiation hazards, providing valuable
planning information for the Oak Ridge and Hanford facilities.
END
|